Pluto LNG Project
Project Service: Industrial construction and non-process infrastructure
Client: Woodside
Location: Burrup Peninsula, Karratha
Start Date: 2008
Completion Date: 2009
Woodside's $12 billion Pluto LNG Project is based on the Burrup Peninsula, Karratha, and is set to become Australia's second biggest resources project.
Woodside has awarded us three contracts for the development of the Pluto LNG Project:
Storage and loading facility
The supply and installation of concrete foundations, pedestals, in-ground electrical and hydraulic services for the project's storage and loading facility.
LNG processing facility
Construction of the temporary site facilities and provide miscellaneous civil works including, buildings to be unloaded, installed and assembled, infrastructure and utilities, including foundations.
Administration buildings
Construction of a 2,000 sq metre building to house Pluto's state-of-the-art central control room and administration. Buildings are constructed as pre-fabricated modules in Perth prior to being transported, installed and commissioned on-site at Pluto's plant on the Burrup Peninsula.
The contract also includes the construction and installation of an adjoining 320 sq metre purpose-built guardhouse/medical facility and the in-situ foundation works required for both buildings