Lang Hancock Railway - Hope Downs Village Project
Project Service: Accommodation
Client: Hamersley Iron
Location: Hope Downs Mine Site, 80km north of Newman, Western Australia
Start Date: 2006
Completion Date: 2007
We were awarded two design and construct contracts simultaneously by Hamersley Iron. The works included supplying and installing a temporary construction village and installing the in-ground services for the temporary and permanent villages for the Lang Hancock Railway Project at the Hope Downs site north of Newman.
In addition, we constructed the permanent village consisting of 352 en-suited concrete floored accommodation rooms, permanent kitchen and dining facilities plus a licensed wet mess and other facilities including the supply and installation of a 14MW power station.